Voltage calibration schedule

Calibration session Calibration start date Deliver standard cells
by date below
Deliver electronic standards
by date below
October 2018 1 October 2018 14 September 2018 26 September 2018
March 2019 4 March 2019 15 February 2019 27 February 2019


Resistance calibration schedule

Nominal value Start date

Week no

100 Ω 8 October 2018 41
25 Ω 15 October 2018 42
10 Ω 29 October 2018 44
1 Ω 5 November 2018
45
1 kΩ 19 November  2018 47
10 kΩ 26 November  2018 48
100 kΩ 7 January 2019 2


Guide dates for early part of 2019

Nominal value Date
1 MΩ January 2019
10 MΩ February 2019
100 MΩ February 2019
1 GΩ March 2019
100 Ω April 2019